The SP Energy webpage / plan only shows where they are laying conduit - SP Energy / Opus are now also pulling cable through the conduit that was laid earlier, with typically traffic light management. This work is only visible via the OneNetwork link.
All work is planned by SP Energy, using the Contractor Opus Energy:
- Email: lymmreinforcement@spenquiries.co.uk
- Phone (Mon-Fri, 9am-5pm): 0800 188 4481
"We currently have two teams working simultaneously on the project in different areas of Lymm. The work is being completed in stages with the aim of keeping disruption to a minimum. We have an on-site manager who will be in the area for the duration of the project during scheduled hours."
The chart below has been put together from the SP Energy dates (before they pulled them!) here: www.spenergynetworks.co.uk/lymm & is 'correct' as at 04/04/2026. The hashed column is LHS Easter Holidays. As above, this is really for information (showing what is still required).